U.S. regulators mull issues around siting data centers at power plants

USA-POWER-CO-LOCATION:U.S. regulators mull issues around siting data centers at power plants

Reuters
Published2 Nov 2024, 01:06 AM IST
U.S. regulators mull issues around siting data centers at power plants
U.S. regulators mull issues around siting data centers at power plants

By Laila Kearney

NEW YORK (Reuters) - Costs and reliability concerns related to the burgeoning trend of building energy-intensive data centers on the sites of U.S. power plants were the focus of a technical conference held on Friday by the Federal Energy Regulatory Commission.

As the technology industry races to deploy data centers needed to roll out technologies like generative artificial intelligence, quickly accessing the massive amounts of electricity needed for the centers has become a critical problem.

Connecting data centers directly to power plants, in an arrangement known as co-location, has presented a fast way to access large amounts of electricity, instead of toiling for years in queues to connect to the broader grid.

"I believe that the federal government, including this agency, should be doing the very best it can to nurture and foster their development," said FERC Chairman Willie Phillips, adding that he considered the AI centers were vital to national security and the country's economy.

The arrangements have sparked concerns that the co-located centers will increase power bills for everyday customers by using grid infrastructure and services paid for by the public. Co-located data centers have also raised reliability questions, in part, by diverting steady power from the grid or potentially sucking electricity from the system if the neighboring power plant goes down.

"Does the customer get to still draw power from the grid? Because if it does, that's going to have a huge impact," said Commissioner Mark Christie.

The technical conference could lead to new guidelines for who is responsible for certain costs related to co-located data centers and how the centers are governed.

FERC is also currently gathering details on a regulatory battle being waged by electric utilities over a co-located Amazon data center at a Talen Energy nuclear power plant in Pennsylvania. Talen's interconnection agreement for the center is being opposed by utilities Exelon and American Electric power, and FERC's decision could set a precedent for similar deals.

(Reporting by Laila Kearney; Editing by David Gregorio)

Catch all the Business News , Breaking News Events and Latest News Updates on Live Mint. Download The Mint News App to get Daily Market Updates.

MoreLess
First Published:2 Nov 2024, 01:06 AM IST
Business NewsNewsU.S. regulators mull issues around siting data centers at power plants

Get Instant Loan up to ₹10 Lakh!

  • Employment Type

    Most Active Stocks

    Power Grid Corporation Of India share price

    338.70
    03:50 PM | 26 NOV 2024
    -4.15 (-1.21%)

    Adani Power share price

    437.75
    03:58 PM | 26 NOV 2024
    -9.1 (-2.04%)

    Bharat Electronics share price

    297.80
    03:54 PM | 26 NOV 2024
    5.35 (1.83%)

    GAIL India share price

    193.90
    03:54 PM | 26 NOV 2024
    -5.25 (-2.64%)
    More Active Stocks

    Market Snapshot

    • Top Gainers
    • Top Losers
    • 52 Week High

    Piramal Enterprises share price

    1,197.35
    03:47 PM | 26 NOV 2024
    89.55 (8.08%)

    Laurus Labs share price

    545.00
    03:29 PM | 26 NOV 2024
    12.85 (2.41%)

    Wipro share price

    589.05
    03:58 PM | 26 NOV 2024
    6.3 (1.08%)

    Federal Bank share price

    213.55
    03:51 PM | 26 NOV 2024
    0.55 (0.26%)
    More from 52 Week High

    Poly Medicure share price

    2,775.00
    03:29 PM | 26 NOV 2024
    -227.7 (-7.58%)

    Adani Green Energy share price

    899.40
    03:59 PM | 26 NOV 2024
    -68.25 (-7.05%)

    DCM Shriram share price

    1,160.00
    03:29 PM | 26 NOV 2024
    -67.3 (-5.48%)

    Fortis Healthcare share price

    664.60
    03:59 PM | 26 NOV 2024
    -36.15 (-5.16%)
    More from Top Losers

    Piramal Enterprises share price

    1,197.35
    03:47 PM | 26 NOV 2024
    89.55 (8.08%)

    Triveni Turbines share price

    824.30
    03:54 PM | 26 NOV 2024
    60.4 (7.91%)

    Capri Global Capital share price

    210.00
    03:29 PM | 26 NOV 2024
    15.35 (7.89%)

    Vodafone Idea share price

    7.53
    03:59 PM | 26 NOV 2024
    0.55 (7.88%)
    More from Top Gainers

    Recommended For You

      More Recommendations

      Gold Prices

      • 24K
      • 22K
      Bangalore
      78,555.00-1,090.00
      Chennai
      78,561.00-1,090.00
      Delhi
      78,713.00-1,090.00
      Kolkata
      78,565.00-1,090.00

      Fuel Price

      • Petrol
      • Diesel
      Bangalore
      102.92/L0.00
      Chennai
      100.90/L0.00
      Kolkata
      104.95/L0.00
      New Delhi
      94.77/L0.00

      Popular in News

        HomeMarketsPremiumInstant LoanMint Shorts